Plans to improve the North Devon Link Road have been downgraded due to rising costs, the county council has announced.
Plans for an underpass at the Bishops Tawton Roundabout have been scrapped as well as a section of overtaking lane between Landkey and Portmore roundabouts.
According to Devon County Council (DCC) rising costs as a result of inflation are behind the decision to amend its ongoing North Devon Link Road improvement plans.
The £67 million improvement programme, the vast majority of which is funded by the Department for Transport, were costed back in 2019 when the economic landscape was very different.
A DCC spokepserson said: "The unexpected coronavirus pandemic, which has had and still is having a dramatic impact on businesses, followed by the unforeseen rise in costs of materials and energy compounded by the war in Ukraine, inflation, and rising interest rates, and £67 million no longer buys as much in 2022 as it did in 2019.
"The entire construction programme is managed within a number of contracts, with one contract in particular accountable for the main work. That’s where the problem is now.
"Due to rising inflation, the contractor’s costs have increased beyond what might usually be expected by more than a quarter, since first costed.
"We have spoken to the Department for Transport, as the main funder for the project, to see if there’s any more funding from them available. There’s not."
Councillor Andrea Davis, Cabinet Member with responsibility for infrastructure, said: “That’s the reality of what’s happening in construction and other business sectors everywhere.
“It means that we’ve had to look within the £67 million budget, outside the scope of the main essential work, to see what we can do differently to reduce costs, that does not compromise the purpose of the improvements.”
In addition to the main improvement work, our plans had been to improve junctions at Heywood, Buckleigh, Westleigh, Bishops Tawton, West Buckland and Borners Bridge.
“To absorb the extra costs within the main contract, we need cut back on costs elsewhere,” said Cllr Davis. “So, we will continue our plans to improve junctions at Heywood, Buckleigh, Westleigh, West Buckland, and Borners Bridge, but we will now redesign the Bishops Tawton Junction, to remove what was to be an underpass, and instead install safe crossing facilities.”
Plans for a section of overtaking lane between Portmore and Landkey roundabouts, and for a footbridge over the road in that vicinity, will however now be removed from the programme. Plans do still include a footbridge located at the Landkey junction.
“We’ve considered all options, not just by cost, but also considering road safety,” says Councillor Davis.
“Removing the overtaking lane and the footbridge and redesigning the junction at Bishops Tawton will allow us to divert funding to the main work, to meet the additional costs of construction.
“With regards to the footbridge, we will be looking for developer contributions in future to help pay for improved walking and cycling access in the area.”
The main works are still on track to be completed by the end of 2023, but the Bishops Tawton junction may be delayed until mid-2024.
Subscribe or register today to discover more from DonegalLive.ie
Buy the e-paper of the Donegal Democrat, Donegal People's Press, Donegal Post and Inish Times here for instant access to Donegal's premier news titles.
Keep up with the latest news from Donegal with our daily newsletter featuring the most important stories of the day delivered to your inbox every evening at 5pm.