First phase of Barnstaple roadworks set to finish early – but more to come


After weeks of disruption the first stage of Bickington roadworks for gas main replacement is done, but a new stretch of road will be restricted to one way from August 24
Major roadworks at Bickington look set to finish a week earlier than scheduled, with residents and commuters gaining a brief respite before the next phase begins.
From Monday (August 17) there will be full access to Bickington and Fremington, but from Monday, August 24 the next stage of the Wales & West Utilities gas main works will begin with a new ‘directional’ road closure in place.
Bickington Road between the Cedars roundabout and the Esso garage will be closed one way, meaning traffic can travel from the Cedars towards Barnstaple.
Those coming from the other direction will have to take a diversion at the ‘Barnhenge’ roundabout and travel on the A39 before turning off at the Roundswell roundabout and taking the B3233 back towards Cedars to enter Bickington.
This directional closure is expected to run until November 8.
Other traffic restrictions associated with this phase of the works include a road closure on Oakland Avenue, where there will be no access onto Bickington Road, plus traffic lights on the junction of Bickington Road and Old Torrington Road.
The project started in mid-June and is part of Wales & West Utilities’ wider work to invest more than £1.8million over the next year to upgrade gas pipes across Bickington and the surrounding areas.
The intensive programme of wider mains replacement works will see more than nine kilometres of gas pipes upgraded across the area, which the company says will benefit approximately 1,000 local customers.
Roxanne Whittaker at Wales & West said: “We are progressing well with our work and want to remind people that businesses remain open whilst we carry out this essential work.
“We understand our work can cause disruption, but it is essential to maintain a resilient gas network that households and business can rely on every day.”
Frank Biederman, the county councillor for Fremington Rural, announced in a Facebook video yesterday the current works looked highly likely to finish a week early.
He said: “The guys have done incredibly well and it does look like they're going to be off site a week early.
“Thank you to everybody that's made such an effort through this period. It has been a long haul, especially those that have volunteered looking after our elderly and vulnerable and everybody that has supported neighbours and the sacrifices you've made, whether it be to work later, work from home, cycle or walk, it’s been amazing.”
Cllr Biederman said he was still trying to find out whether the public bus service would revert to its normal route, bar serving a couple of bus stops at Sticklepath.
Wales & West Utilities said people can keep up to date with projects in their area at https://www.wwutilities.co.uk/services/gas-pipe-upgrades