Developer will appeal decision on controversial battery storage site


Plans for a 10-acre battery energy storage site at Alverdiscott will now go to appeal after being turned down by Torridge District Council
An appeal has been lodged following Torridge District Council’s refusal of a battery energy storage system (BESS) site near Alverdiscott last month.
The council’s planning committee rejected the 99 MW scheme for 10 acres on West Webbery Farm at Woodtown because they said the impact and harm on the landscape “outweighed” any benefits.
There were also objections from 64 members of the public.
The main area of concern was the cumulative effect of solar and battery storage developments in the parish of Alverdiscott.
The location of the Alverdiscott substation in a valley to the east has recently led to a cluster of applications for energy provision.
A planning inspector will now decide whether the committee was right in its decision to refuse permission or choose to overturn it following an appeal by the applicants.
Expanding battery storage capacity is claimed to be critical to future energy security.
BESS sites contain thousands of lithium-ion batteries, which store energy from renewable sources such as wind and solar and release it back into the grid when demand is high.
But Torridge councillor Thomas Elliot said at a planning meeting on July 2 the parish was “being hammered, left right and centre” and feared there would be very little of the rural scenery left if more developments of this nature were allowed.
Members went against the planning officer’s recommendation to grant approval and refused the proposal by eight votes to one.
Speaking at the meeting, dairy farmer Ian Ratcliffe said the proposal would help him keep farming at a challenging time for the industry, allowing him to diversify on less than one per cent of the 615 acres he managed and in years to come the site would be returned to its original use.
Countryside charity CPRE Devon has been leading the fight against a growing number of solar and battery applications in the area and held a demonstration at the planning meeting where local people turned up with placards.
The charity has claimed there was no need for the BESS and said according to current data from the National Energy System Operator NESO it would not be connected to the grid for another 10 years.
CPRE Devon is currently opposing plans for a 49.9MW solar and BESS application at Bulworthy Farm nearby.
Another BESS site and AI data centre plan are due to be submitted later this year for the edge of the village, which would be spread across 850 acres.
A Devon CPRE spokesperson said: “We are extremely concerned about the growing number of solar and battery applications in a concentrated cluster of development around Alverdiscott – a honeypot for investors seeking to cash in on the ‘solar and battery gold rush’.”
CPRE Devon called TDC’s decision in July a victory for people power.
The public can comment on the appeal until midnight on September 16 at https://appeal-planning-decision.service.gov.uk/comment-planning-appeal/appeals/6013918