Funding agreed for upgrades to North Devon Crematorium


North Devon and Torridge district councils have agreed more than £600,000 in funding to pay for much-needed works at the region’s only crematorium
The region’s district councils have agreed funding to finish a £2million upgrade to North Devon Crematorium.
The facility in Barnstaple has been jointly owned by Torridge and North Devon councils since 1974 but the cremators are badly in need of replacing and the car park needs resurfacing to cope with the amount of vehicles that arrive there.
At full council meetings this week Torridge members approved a contribution of £262,000 (40 per cent) and the larger North Devon Council £393,000 (60 per cent) towards the two requirements.
The money will meet a funding gap in reserves for infrastructure improvements.
Councillors heard the current cremators which had been in place since 2012, including one purchased as refurbished, kept breaking down and fixes were only temporary and costly.
Councillor Helen Walker, chair of the crematorium joint committee, told North Devon Council (NDC) that income from the facility pays a “substantial amount” into the councils’ revenue budget each year whilst still remaining “extremely competitive with other facilities in the area.”
The new ‘hybrid’ equipment would be more economical to run, more efficient, require less maintenance and produce far less emissions.
The mix of tarmacked and gravel car park areas needed resurfacing, remarking and lining, a new layout and drainage improvements. Entrances and exits had deep potholes and dipped areas.
A report to NDC said the proposed improvements would be staggered to minimise disruption for families and mourners and they would all be complete by the end of summer 2027. A containerised cremator will be put in place to ensure capacity is retained throughout the period.
These proposals form part of a wider improvement programme of works, including a recently installed ‘cold’ facility which allows the councils to offer a new service to funeral directors for overnight storage as well as improving its business continuity position.
A more welcoming entrance and solar panels had been installed as part of the £2million refurbishment to help make it fit for purpose for the future.
Members supported the financial contributions.