A million-pound project to repair the quay wall at Brunswick Wharf in East the Water, Bideford will begin in April. The renovations alongside the River Torridge must happen before developers Red Earth can begin their work to build apartments, shops, desi

A million-pound project to repair the quay wall at Brunswick Wharf in East the Water, Bideford will begin in April.

The renovations alongside the River Torridge must happen before developers Red Earth can begin their work to build apartments, shops, design spaces and a public square on the redundant site.

Founder of Red Earth, Simon Friend, said: “I am delighted that after a protracted delay, we have been able to work successfully with Torridge District Council to enable these works to start, which are a key element for the success of the overall development. The repairs will take some three to four months and although a section of the car park on the river side will need to be closed off, the remaining parking and activity around Brunswick Wharf will be able to function and continue as normal.”

The harbour wall works were scheduled to have begun last year. But an agreement has now been reached between Red Earth and Torridge District Council about the terms of the Land Release Fund Grant. It was awarded by the Department for Levelling Up, Housing and Communities to meet its aims of bringing forward housing schemes where key infrastructure costs are causing a delay.placeholder image
The harbour wall works were scheduled to have begun last year. But an agreement has now been reached between Red Earth and Torridge District Council about the terms of the Land Release Fund Grant. It was awarded by the Department for Levelling Up, Housing and Communities to meet its aims of bringing forward housing schemes where key infrastructure costs are causing a delay.

The Grant amounts to £797,000 and following a Full Torridge District Council vote at its meeting in January this year, the funding will be released in stages to coincide with the completion of the harbour wall repair works and the start on site of the main development. The balance of the total costs, which will be just under £1,000,000, will be met by Red Earth.

The construction contract is being placed with TMS Ltd who have more than 30 years of expertise as a Marine Contractor within Civil Engineering. Chris Lonsdale of TMS said: “TMS Maritime is thrilled to be working with Red Earth to repair the existing masonry harbour wall at Brunswick Wharf. This important part of the project will provide greater resilience to the quayside and will enhance the town’s waterfront aspect in preparation for the prestigious main development scheme.”

Simon Friend added: “Despite construction costs being extremely challenging at the moment, and ongoing uncertainty in the economy generally, we are committed to seeing this project through to completion. We are hoping to start the main construction works in 2024. A project of this size with an investment of around £30 million is hugely significant for the area and I am very grateful for everyone’s patience as we work hard towards making this a reality.”